View from top of the MSU track grandstand - Jan 13, 2012
View from the top of the MSU track grandstand - Jan 13, 2012
View from the top of the MSU track grandstand - Jan 13, 2012
View from the top of the MSU track grandstand - Jan 13, 2012
View from the practice field north of the football building - Jan 13, 2012
Closer view from the football practice field -Jan 13, 2012
Closer view from the football practice field -Jan 13, 2012
Closer view from the football practice field -Jan 13, 2012
View from the MSU baseball grandstand - Jan 13, 2012
Closer view from the MSU baseball grandstand - Jan 13, 2012
Closer view from the MSU baseball grandstand - Jan 13, 2012
Closer view from the MSU baseball grandstand - Jan 13, 2012
Dirt is being filled into spaces next to the retaining wall - Jan 13, 2012
Steel columns were installed Thursday, four days ahead of schedule - Jan 13, 2012
Closer view of first steel column being installed today (Friday, Jan 13th) - Jan 13, 2012
Rebar in the weight room area of the building. Concrete will be filled in this hole in the next day or two - Jan 13, 2012